LIVE: NASA on results of second rehearsal for Artemis II
TL;DR
NASA officials confirmed the successful completion of Artemis II's second wet dress rehearsal, resolving previous hydrogen seal leaks and validating launch countdown procedures. The agency is now targeting March 6 as the earliest launch date, pending a Flight Readiness Review and final pad preparations.
🚀 Wet Dress Rehearsal 2 Success 3 insights
Full tanking completed on schedule
The SLS rocket was fully loaded with cryogenic propellants within the planned timeline, demonstrating successful preparation for launch day operations.
Launch countdown validated with new procedures
The team successfully demonstrated the terminal count sequence including a first-ever 3-minute MPS hold constraint and completed a recycle procedure with cryogenically fueled hardware in 57 minutes.
Crew module closeout demonstrated
The closeout crew successfully performed all activities to seal the Orion crew module hatch within timeline parameters.
đź”§ Technical Fixes and Performance 3 insights
Seal replacements eliminated hydrogen leaks
Engineers replaced both 8-inch and 4-inch seals at the quick disconnect interface, reducing leak rates to approximately 1% or less—well below the 16% limit and significantly improved from Wet Dress Rehearsal 1.
Pre-test hydrogen integrity test confirmed fixes
A mini-tanking test conducted between rehearsals helped pinpoint the 8-inch seal as the primary leak source, validating the remediation strategy before full vehicle loading.
Minor communication issue unrelated to tanking
The only significant anomaly during the test involved a comm system issue that did not impact cryogenic loading operations or vehicle systems.
đź“… Path to Launch 3 insights
March 6 targeted as earliest launch attempt
Following the successful rehearsal, NASA established March 6 as the target launch date contingent on completing a multi-day Flight Readiness Review scheduled for the end of next week.
Critical pad work remains
Before launch, teams must install contingency pad access platforms and complete a Flight Termination System retest, requiring several days of work at Launch Pad 39B.
Crew enters pre-launch quarantine
Astronauts Reid Wiseman, Christina Koch, and Jeremy Hansen began soft quarantine at Johnson Space Center and will transfer to Kennedy Space Center approximately five days before launch.
Bottom Line
With critical seal leaks resolved and launch procedures validated through successful wet dress rehearsal, NASA is positioned for a March 6 launch attempt assuming the upcoming Flight Readiness Review and final pad preparations are completed without issue.
More from Reuters
View all
LIVE: British PM Starmer takes questions in parliament
Prime Minister Keir Starmer defended his refusal to directly approve new North Sea oil licenses, citing legal constraints and advocating for renewables, while clashing with opposition leader Kemi Badenoch over energy security and the UK's stance on the Iran-Israel conflict.
LIVE: Lagarde addresses the 'ECB and Its Watchers' conference at Frankfurt University
ECB President Christine Lagarde outlined a scenario-based strategy to navigate the latest Middle East energy shock, emphasizing three core principles—assessing shock persistence, monitoring tail risks beyond baseline forecasts, and maintaining graduated policy options—while noting today's neutral policy stance and weaker demand reduce the risk of 2022-style inflationary pass-through.
LIVE: UNHRC holds emergency debate on Iran
The UN Human Rights Council convened an emergency debate on escalating military hostilities where Iran launched drone and missile attacks against Gulf Cooperation Council states and Jordan following US and Israeli strikes, as UN officials warned of catastrophic civilian casualties, potential war crimes, and severe global economic disruptions from the closure of the Strait of Hormuz.
LIVE: NASA provides update on National Space Policy
NASA Administrator Jared Isaacman outlined a strategic pivot to prioritize a lunar surface base over the Gateway orbital outpost, emphasizing that the agency will fund these ambitions by reallocating its existing $25 billion annual budget and leveraging commercial partnerships rather than seeking new congressional appropriations.